Nuclear power as we know it is finished

Nuclear power as we know it is finished
By Chris TomlinsonAugust 3, 2017
Let it be written that environmentalists didn’t kill the nuclear power industry, economics did.

South Carolina Electric and Gas Co. and partner Santee Cooper abandoned work on two new nuclear reactors this week, not because of public protests, but because the only way to pay for them was to overcharge customers or bankrupt both companies.

The decision comes after the main contractor, Westinghouse, has completed a third of the work at the V.C. Sumner Nuclear Station. Of course, the project has already bankrupted Westinghouse due to missed deadlines and costs spiraling out of control. Westinghouse parent Toshiba Corp. had to pay $2.7 billion to get out of it’s contract.

via Nuclear power as we know it is finished – Houston Chronicle